Chapter 12

Risks, safety and quality

Risk register, safety rules and quality assurance.

This chapter lists the main technical and organisational risks, the safety rules for laboratory and field work, and the quality measures that support the results.

12.1Risk register

Probability (P) and impact (I) are rated from 1 (low) to 3 (high); the score is their product. The register is reviewed monthly (WP0).

Table 12.1.Risk register, sorted by score.

IDRiskPIScoreMitigationOwner
R2Coil nulling does not reach 10⁻³ at all tones236Adjustable overlap fixture; background subtraction per tone; gradiometer receiver pairHW
R4Measured spectra do not match the model at M1236Gate G1 with diagnosis time; independent reproduction; empirical calibration as fallbackPI
R7Dataset too small for the classification targets236Simulation; object-level augmentation; extension at gate G3DS
R15Grant not awarded, or awarded later or smaller than requested236Applications to several programmes in parallel (Chapter 11); a national grant funds WP1 and WP2 first; work packages can start in sequence as funds arrivePI
R1Codec input noise or full-scale voltage worse than derived224The ×33 preamplifier is part of the design from the start; lower-noise op-amp option; measured in T1.3HW
R3Ground response larger than estimated, reducing range224Measured at two sites early (T2.6); spectral ground fitting; shallower test beds if neededDS
R5RTK fix unavailable under trees or near buildings224Open test sites; camera and IMU bridging; wheeled cart with odometry (G2)SW
R9Second AD9363 receive channel unavailable or phase unstable224Reference by switched loopback; radar scope reduced at gate G4HW
R10Procurement or customs delays224Long-lead items ordered in week 1; local alternatives; slack in WP3 and WP5PI
R8Copper and aluminium cannot be separated313Not required by any milestone; achieved separability is reportedPI
R11Loss of a team member133Two owners per work package; lab and decision logs; contingency for a contractorPI
R14Safety incident during field work133Field rules in Chapter 12; only cleared land; safety briefing for every participantHW
R6Magnetometer disturbed by the transmitter or by steel on site212Mounted at least 50 cm above the coil; heading from RTK track and camera odometrySW
R12Host cannot sustain six-channel streaming122Both hosts tested in T1.2; reduced sample rate as fallbackSW
R13Radar emission outside permitted limits122Low power, shielded antennas facing the ground; regulations checked in T5.4HW

12.2Safety

12.2.1Field work and ordnance

LODESTONE is a research instrument and is not a mine or ordnance detector. Several regions have known or suspected contamination with landmines and unexploded ordnance. The following rules apply without exception:

12.2.2Electrical

12.2.3Radio emissions

The radar sweeps 0.5 to 3 GHz and crosses bands used by mobile networks and satellite navigation. Ground-penetrating radar is a regulated device class in most countries. Transmit power is kept at the minimum needed, antennas are shielded and directed into the ground, and sweeps run only during measurements. The applicable national regulations are checked before field use (T5.4).

12.3Quality assurance

12.4Open technical questions

  1. Actual input noise and full-scale voltage of the CS42448 board (T1.3).
  2. Whether 96 kHz sampling is reliable on the chosen host (T1.3).
  3. The ground-response factor at the test sites, which sets the detection range (T2.6).
  4. Achievable depth accuracy from peak width, which determines whether copper and aluminium can be distinguished (T3.7).
  5. Phase behaviour of the AD9363 synthesisers on the available Pluto unit and availability of the second channel (T5.1).
  6. RTK availability at the test sites (T3.2).