The project runs for 52 weeks with a team of four (Chapter 10). The work is divided into seven work packages: a continuous management package (WP0) and six technical packages. Each technical package ends with a measurable milestone. Four decision gates define what happens if a milestone is missed.
9.1Structure and logic
The order of the work follows the dependencies between measurements. The receive chain must work (WP1) before the static rig can be calibrated against theory (WP2). The full-tensor dataset (WP4) needs a calibrated rig and, for tracked captures, the positioning platform (WP3). The radar (WP5) is developed in parallel because it has no dependency on the induction hardware. Fusion, field trials and release (WP6) close the project.
Table 9.1.Work packages.
| WP | Title | Lead | Weeks | Objective |
|---|---|---|---|---|
| WP0 | Project management | PI | 1–52 | Planning, reviews, procurement, documentation, reporting |
| WP1 | Bring-up and receive chain | HW | 1–8 | Working codec, coils and preamplifiers with measured characteristics |
| WP2 | Static induction rig and calibration | PI | 6–18 | Measured sphere spectra agreeing with the exact model |
| WP3 | Positioning and timing platform | SW | 10–26 | Pose of the coil at every block to 2 cm |
| WP4 | Full tensor, dataset and classification | DS | 18–36 | Labelled dataset and a classifier validated on unseen objects |
| WP5 | Radar subsystem | HW | 22–40 | SFCW radar imaging metal targets at 35 cm |
| WP6 | Fusion, field trials and release | PI | 36–52 | Fused system tested in the field; public release |
9.2Schedule
9.3Tasks
Each task has one responsible owner (see the role codes in Chapter 10), a time window and a defined result. The acceptance criterion states how completion is checked.
Table 9.2.Tasks with owner, supporting role, time window and acceptance criterion.
| ID | Task | Lead | Support | Weeks | Acceptance criterion / result |
|---|---|---|---|---|---|
| WP0 · Project management (lead PI, weeks 1–52) | |||||
| T0.1 | Kick-off; project handbook, repository and data conventions | PI | all | 1–3 | Handbook D0.1 agreed by all four team members |
| T0.2 | Procurement and budget control | PI | SW | 1–52 | Orders placed per procurement schedule; monthly spending report |
| T0.3 | Weekly meetings, monthly reviews, risk and decision logs | PI | all | 1–52 | Minutes and logs up to date at every monthly review |
| T0.4 | Maintenance of this report; quarterly reports | PI | DS | 1–52 | Report revised monthly; quarterly reports on time |
| WP1 · Bring-up and receive chain (lead HW, weeks 1–8) | |||||
| T1.1 | Bench set-up: instruments, supplies, single-point grounding | HW | – | 1–2 | Bench ready; ground scheme documented |
| T1.2 | Codec bring-up on Teensy 4.1 and Raspberry Pi; host decision | SW | HW | 1–4 | All 14 channels verified in loopback; no lost samples in 1 h; host chosen |
| T1.3 | Codec characterisation: full scale, input noise, coupling corner, 96 kHz test | HW | SW | 3–5 | Measured values replace datasheet values in Chapter 5 (D1.1) |
| T1.4 | Wind and measure transmit and receive coils | HW | – | 2–5 | Self-resonance at least 400 kHz; inductance within 10% of 4.58 mH |
| T1.5 | Preamplifier and calibration-injector PCB: design, fabrication, test | HW | SW | 3–8 | Input noise at most 3 nV/√Hz; channel gains matched within 1% (D1.2) |
| T1.6 | Acquisition software: tone generation, block demodulation, logging | SW | DS | 2–7 | 12-tone loopback stable to 0.1% amplitude and 0.1° phase over 10 min |
| WP2 · Static induction rig and calibration (lead PI, weeks 6–18) | |||||
| T2.1 | Transmit driver: class-D amplifier, series resistor, current sense, soft ramps | HW | – | 6–9 | 1 A per coil without clipping at crest factor 3.1 |
| T2.2 | Coil geometry and nulling fixture | HW | PI | 8–13 | Direct coupling at most 10⁻³ at all 12 tones (D2.2) |
| T2.3 | Forward model: exact sphere, dipole model, coil geometry | PI | – | 6–10 | Model reproduces the three analytic limits and published examples |
| T2.4 | Calibration measurements with four sphere types at 10, 20 and 30 cm | PI | DS | 13–16 | Complete data set including repeat measurements |
| T2.5 | Comparison with the model; systematic error budget | PI | DS | 15–18 | M1 criterion evaluated; calibration report D2.1 |
| T2.6 | Ground survey at two sites; ground-response factor | DS | HW | 14–18 | Background spectra and measured ground factor for both sites |
| WP3 · Positioning and timing platform (lead SW, weeks 10–26) | |||||
| T3.1 | Sensor pole: non-metallic structure, mounts, lever arm | HW | – | 10–13 | Rotation test: computed coil position stays within a 2 cm circle |
| T3.2 | RTK base and rover, correction link, availability survey | SW | – | 10–14 | Fixed solution for at least 95% of the time at the test sites |
| T3.3 | PPS timing into codec and camera | SW | – | 12–16 | Timing error at most one sample against GNSS time tags |
| T3.4 | IMU and magnetometer integration; interference test with transmitter on | SW | HW | 13–16 | Heading change at most 1° when the transmitter switches on |
| T3.5 | Camera visual-inertial odometry with height scaling | DS | SW | 14–20 | Drift at most 1% of distance on a 20 m test track |
| T3.6 | Extended Kalman filter: RTK, IMU, camera, magnetometer, height | SW | DS | 16–24 | Continuous pose at block rate (D3.1) |
| T3.7 | Tracked-pass validation: peak width against depth, repeatability | PI | DS | 22–26 | M2 criterion evaluated; validation report D3.2 |
| WP4 · Full tensor, dataset and classification (lead DS, weeks 18–36) | |||||
| T4.1 | Three-axis transmit head with interleaved tone sets | HW | SW | 18–24 | Cross-talk between transmitters at most -60 dB after FFT separation |
| T4.2 | Tensor inversion software | PI | DS | 20–28 | Simulated tensors recovered within 5% at 30 dB SNR (D4.2) |
| T4.3 | Simulator: spheres, spheroids, finite-element shapes; noise and soil | DS | PI | 20–30 | 10,000 simulated captures; agreement with calibration data |
| T4.4 | Dataset collection: at least 30 objects, 500 captures, 2 soils | DS | all | 24–34 | Dataset v1 with metadata and data sheet (D4.1) |
| T4.5 | Classifiers: gradient boosting baseline, 1D-CNN comparison | DS | PI | 28–35 | Cross-validated accuracy with confidence intervals |
| T4.6 | Blind test on hidden objects | DS | HW | 34–36 | M3 criterion evaluated; blind-test report D4.3 |
| WP5 · Radar subsystem (lead HW, weeks 22–40) | |||||
| T5.1 | Pluto set-up: firmware profile, two-channel mode, coupler loopback | HW | SW | 22–25 | Reference-corrected phase stable within 2° over 100 retunes |
| T5.2 | Vivaldi antennas: simulation, fabrication, measurement | HW | – | 22–30 | S11 at most -10 dB from 0.5 to 3 GHz |
| T5.3 | Sweep software, background subtraction, range profiles | SW | PI | 24–32 | Metal plate in air at the correct range within 2 cm |
| T5.4 | Amplifiers, shielding and emission check | HW | – | 30–33 | Emission within applicable limits; radar hardware D5.1 |
| T5.5 | Sandbox radar tests along tracked passes | PI | DS | 32–40 | M4 criterion evaluated; radar report D5.2 |
| WP6 · Fusion, field trials and release (lead PI, weeks 36–52) | |||||
| T6.1 | Fusion of induction and radar detections | DS | PI | 36–44 | Fused false-alarm rate lower than either sensor alone |
| T6.2 | Live map and operator interface | SW | – | 38–46 | Map updated within 1 s of acquisition during a pass |
| T6.3 | Field trials at two sites with seeded targets | PI | all | 42–48 | Trial report with ground truth by excavation (D6.1) |
| T6.4 | Documentation of hardware, software and dataset | SW | all | 40–52 | An outside reader rebuilds the receive chain from the documents |
| T6.5 | Review of patents and non-English literature | PI | – | 40–44 | Review added to Chapter 2 |
| T6.6 | Paper preparation and submission | PI | all | 44–52 | Paper submitted (D6.2) |
| T6.7 | Public release of designs, code, dataset and report | SW | all | 50–52 | Release published (D6.3); M5 |
9.4Milestones
Table 9.3.Milestones and acceptance criteria.
| ID | Week | Milestone | Criterion | Verification | Owner |
|---|---|---|---|---|---|
| M1 | 18 | Calibration agrees with theory | Spectra of the four calibration spheres agree with the exact model within ±10% in amplitude and ±5° in phase at all 12 tones, at 10 and 20 cm | Calibration report D2.1, reproduced independently from raw data by DS | PI |
| M2 | 26 | Positioning validated | Ten passes over a marked target from different headings give positions within 2 cm (1σ); depth from peak width within ±1.5 cm at 20 cm | Validation report D3.2 | SW |
| M3 | 36 | Classifier validated on unseen objects | Blind test: ferrous / non-ferrous accuracy at least 95%, shape class at least 85%, size within ±25% for at least 80% of objects | Blind-test report D4.3; objects hidden by HW | DS |
| M4 | 40 | Radar imaging | A metal can of about 10 cm buried at 35 cm in dry sand is detected and located; depth error at most 3 cm; echo polarity identified as metal | Radar report D5.2 | HW |
| M5 | 52 | Fused demonstration and release | Live fused survey of a seeded 5 m × 5 m plot; designs, software, dataset and report published | Public repository; field-trial report D6.1 | PI |
9.5Decision gates
At each gate the team reviews the milestone evidence and chooses one of the prepared options. Decisions and their reasons are recorded in the decision log.
Table 9.4.Decision gates.
| Gate | Week | Condition | If met | If not met |
|---|---|---|---|---|
| G1 | 18 | M1 met | Full-tensor work (WP4) starts as planned | Up to 4 weeks of diagnosis of model or hardware; WP4 start moves accordingly, WP3 continues. If still not met in week 22, the dataset uses empirically calibrated spectra and the discrepancy is reported. |
| G2 | 26 | M2 met | Tracked dataset collection with the hand-held pole | A wheeled cart with odometry replaces the hand-held pole; RTK used for start and end points of each track. |
| G3 | 36 | M3 met | WP6 proceeds as planned | Data collection extended by 4 weeks; the operator interface (T6.2) is reduced to a minimum. |
| G4 | 40 | M4 met | Radar included in fusion and field trials | Induction-only results are published; the radar is reported as a partial result and future work. |
9.6Critical path and dependencies
The critical path runs T1.2 → T1.5 → T2.2 → T2.4 → M1 → T4.1 → T4.4 → T4.5 → M3 → T6.1 → T6.3 → M5. Its slack is small: a delay in nulling the coils (T2.2) or in the calibration measurements (T2.4) moves the dataset collection and all later work. The positioning platform (WP3) and the radar (WP5) have about four weeks of slack each. The main external dependency is procurement of the RTK receivers and printed circuit boards, which is started in week 1 (T0.2).
Table 9.5.Procurement schedule.
| Item | Order in week | Needed in week | Remark |
|---|---|---|---|
| Teensy 4.1, op-amps, passives, connectors | 1 | 2 | Local or fast-shipping distributors |
| Magnet wire, foil, coil formers | 1 | 2 | |
| Preamplifier PCB, first run | 4 | 6 | Design completed in T1.5 |
| Class-D amplifier modules, sense resistors | 3 | 6 | |
| RTK receivers, antennas, radio link | 1 | 10 | Longest lead time, import |
| IMU, magnetometer, camera, ranger | 6 | 12 | |
| Calibration spheres, test objects, sandbox | 6 | 12 | |
| Vivaldi antenna PCBs, RF cables, coupler | 20 | 24 | After simulation in T5.2 |
| Second PCB run (revised preamp, tensor head) | 16 | 20 |
9.7Deliverables
Table 9.6.Deliverables.
| ID | Deliverable | Type | Due week | Owner |
|---|---|---|---|---|
| D0.1 | Project handbook: lab-log template, data conventions, safety rules | Document | 3 | PI |
| D1.1 | Codec bring-up and characterisation report | Report | 5 | SW |
| D1.2 | Preamplifier and calibration-injector PCB, revision A | Hardware | 8 | HW |
| D2.2 | Static induction rig (1 TX + 3 RX), documented | Hardware | 13 | HW |
| D2.1 | Calibration report: measured sphere spectra against the model | Report | 18 | PI |
| D3.1 | Positioning and timing platform with fusion software | Hardware, software | 24 | SW |
| D3.2 | Tracked-pass validation report | Report | 26 | PI |
| D4.2 | Tensor inversion software | Software | 28 | PI |
| D5.1 | Radar hardware: antennas, amplifiers, coupler | Hardware | 33 | HW |
| D4.1 | Labelled dataset, version 1 | Data | 34 | DS |
| D4.3 | Classifier and blind-test report | Report | 36 | DS |
| D5.2 | Radar software and test report | Software, report | 40 | PI |
| D6.1 | Field-trial report of the fused system | Report | 48 | DS |
| D6.2 | Paper submitted to a journal or conference | Publication | 52 | PI |
| D6.3 | Public release: designs, code, dataset, report | Release | 52 | SW |
9.8Reporting and reviews
- Weekly: one-hour team meeting (progress against tasks, blockers, next week's measurements). Short written notes are added to the lab log.
- Every two weeks: demonstration of a working result on real hardware or real data.
- Monthly: review of schedule, budget and risk register; update of this report.
- At each milestone: milestone review with a written report, followed by the decision gate where one applies.
- Quarterly: progress report to the funder with spending against budget.