Chapter 9

Work plan

Work packages, tasks, schedule, milestones and decision gates.

The project runs for 52 weeks with a team of four (Chapter 10). The work is divided into seven work packages: a continuous management package (WP0) and six technical packages. Each technical package ends with a measurable milestone. Four decision gates define what happens if a milestone is missed.

9.1Structure and logic

The order of the work follows the dependencies between measurements. The receive chain must work (WP1) before the static rig can be calibrated against theory (WP2). The full-tensor dataset (WP4) needs a calibrated rig and, for tracked captures, the positioning platform (WP3). The radar (WP5) is developed in parallel because it has no dependency on the induction hardware. Fusion, field trials and release (WP6) close the project.

Table 9.1.Work packages.

WPTitleLeadWeeksObjective
WP0Project managementPI1–52Planning, reviews, procurement, documentation, reporting
WP1Bring-up and receive chainHW1–8Working codec, coils and preamplifiers with measured characteristics
WP2Static induction rig and calibrationPI6–18Measured sphere spectra agreeing with the exact model
WP3Positioning and timing platformSW10–26Pose of the coil at every block to 2 cm
WP4Full tensor, dataset and classificationDS18–36Labelled dataset and a classifier validated on unseen objects
WP5Radar subsystemHW22–40SFCW radar imaging metal targets at 35 cm
WP6Fusion, field trials and releasePI36–52Fused system tested in the field; public release

9.2Schedule

Q1Q2Q3Q4481216202428323640444852weekWP0 Project managementT0.1 Kick-off, handbookT0.2 Procurement, budget controlT0.3 Meetings, reviews, logsT0.4 Report and reportingWP1 Bring-up and receive chainT1.1 Bench set-upT1.2 Codec bring-up, host choiceT1.3 Codec characterisationT1.4 Wind and measure coilsT1.5 Preamplifier PCBT1.6 Acquisition software v1WP2 Static induction rig and calibrationM1T2.1 Transmit driverT2.2 Coil nulling fixtureT2.3 Forward modelT2.4 Calibration measurementsT2.5 Model comparisonT2.6 Ground surveyWP3 Positioning and timing platformM2T3.1 Sensor poleT3.2 RTK base and roverT3.3 PPS timingT3.4 IMU and magnetometerT3.5 Camera odometryT3.6 Fusion filterT3.7 Tracked-pass validationWP4 Full tensor, dataset and classificationM3T4.1 Three-axis transmit headT4.2 Tensor inversionT4.3 SimulatorT4.4 Dataset collectionT4.5 ClassifiersT4.6 Blind testWP5 Radar subsystemM4T5.1 Pluto set-up, referenceT5.2 Vivaldi antennasT5.3 Radar softwareT5.4 Amplifiers, emission checkT5.5 Sandbox radar testsWP6 Fusion, field trials and releaseM5T6.1 Induction-radar fusionT6.2 Live mapT6.3 Field trialsT6.4 DocumentationT6.5 Patent and literature reviewT6.6 PaperT6.7 Public releasePI leadHW leadSW leadDS leadmilestonework package
Figure 9.1.Schedule at task level. Bars are coloured by the role that leads the task; diamonds mark milestones; weeks 1 to 52.

9.3Tasks

Each task has one responsible owner (see the role codes in Chapter 10), a time window and a defined result. The acceptance criterion states how completion is checked.

Table 9.2.Tasks with owner, supporting role, time window and acceptance criterion.

IDTaskLeadSupportWeeksAcceptance criterion / result
WP0 · Project management (lead PI, weeks 1–52)
T0.1Kick-off; project handbook, repository and data conventionsPIall1–3Handbook D0.1 agreed by all four team members
T0.2Procurement and budget controlPISW1–52Orders placed per procurement schedule; monthly spending report
T0.3Weekly meetings, monthly reviews, risk and decision logsPIall1–52Minutes and logs up to date at every monthly review
T0.4Maintenance of this report; quarterly reportsPIDS1–52Report revised monthly; quarterly reports on time
WP1 · Bring-up and receive chain (lead HW, weeks 1–8)
T1.1Bench set-up: instruments, supplies, single-point groundingHW–1–2Bench ready; ground scheme documented
T1.2Codec bring-up on Teensy 4.1 and Raspberry Pi; host decisionSWHW1–4All 14 channels verified in loopback; no lost samples in 1 h; host chosen
T1.3Codec characterisation: full scale, input noise, coupling corner, 96 kHz testHWSW3–5Measured values replace datasheet values in Chapter 5 (D1.1)
T1.4Wind and measure transmit and receive coilsHW–2–5Self-resonance at least 400 kHz; inductance within 10% of 4.58 mH
T1.5Preamplifier and calibration-injector PCB: design, fabrication, testHWSW3–8Input noise at most 3 nV/√Hz; channel gains matched within 1% (D1.2)
T1.6Acquisition software: tone generation, block demodulation, loggingSWDS2–712-tone loopback stable to 0.1% amplitude and 0.1° phase over 10 min
WP2 · Static induction rig and calibration (lead PI, weeks 6–18)
T2.1Transmit driver: class-D amplifier, series resistor, current sense, soft rampsHW–6–91 A per coil without clipping at crest factor 3.1
T2.2Coil geometry and nulling fixtureHWPI8–13Direct coupling at most 10⁻³ at all 12 tones (D2.2)
T2.3Forward model: exact sphere, dipole model, coil geometryPI–6–10Model reproduces the three analytic limits and published examples
T2.4Calibration measurements with four sphere types at 10, 20 and 30 cmPIDS13–16Complete data set including repeat measurements
T2.5Comparison with the model; systematic error budgetPIDS15–18M1 criterion evaluated; calibration report D2.1
T2.6Ground survey at two sites; ground-response factorDSHW14–18Background spectra and measured ground factor for both sites
WP3 · Positioning and timing platform (lead SW, weeks 10–26)
T3.1Sensor pole: non-metallic structure, mounts, lever armHW–10–13Rotation test: computed coil position stays within a 2 cm circle
T3.2RTK base and rover, correction link, availability surveySW–10–14Fixed solution for at least 95% of the time at the test sites
T3.3PPS timing into codec and cameraSW–12–16Timing error at most one sample against GNSS time tags
T3.4IMU and magnetometer integration; interference test with transmitter onSWHW13–16Heading change at most 1° when the transmitter switches on
T3.5Camera visual-inertial odometry with height scalingDSSW14–20Drift at most 1% of distance on a 20 m test track
T3.6Extended Kalman filter: RTK, IMU, camera, magnetometer, heightSWDS16–24Continuous pose at block rate (D3.1)
T3.7Tracked-pass validation: peak width against depth, repeatabilityPIDS22–26M2 criterion evaluated; validation report D3.2
WP4 · Full tensor, dataset and classification (lead DS, weeks 18–36)
T4.1Three-axis transmit head with interleaved tone setsHWSW18–24Cross-talk between transmitters at most -60 dB after FFT separation
T4.2Tensor inversion softwarePIDS20–28Simulated tensors recovered within 5% at 30 dB SNR (D4.2)
T4.3Simulator: spheres, spheroids, finite-element shapes; noise and soilDSPI20–3010,000 simulated captures; agreement with calibration data
T4.4Dataset collection: at least 30 objects, 500 captures, 2 soilsDSall24–34Dataset v1 with metadata and data sheet (D4.1)
T4.5Classifiers: gradient boosting baseline, 1D-CNN comparisonDSPI28–35Cross-validated accuracy with confidence intervals
T4.6Blind test on hidden objectsDSHW34–36M3 criterion evaluated; blind-test report D4.3
WP5 · Radar subsystem (lead HW, weeks 22–40)
T5.1Pluto set-up: firmware profile, two-channel mode, coupler loopbackHWSW22–25Reference-corrected phase stable within 2° over 100 retunes
T5.2Vivaldi antennas: simulation, fabrication, measurementHW–22–30S11 at most -10 dB from 0.5 to 3 GHz
T5.3Sweep software, background subtraction, range profilesSWPI24–32Metal plate in air at the correct range within 2 cm
T5.4Amplifiers, shielding and emission checkHW–30–33Emission within applicable limits; radar hardware D5.1
T5.5Sandbox radar tests along tracked passesPIDS32–40M4 criterion evaluated; radar report D5.2
WP6 · Fusion, field trials and release (lead PI, weeks 36–52)
T6.1Fusion of induction and radar detectionsDSPI36–44Fused false-alarm rate lower than either sensor alone
T6.2Live map and operator interfaceSW–38–46Map updated within 1 s of acquisition during a pass
T6.3Field trials at two sites with seeded targetsPIall42–48Trial report with ground truth by excavation (D6.1)
T6.4Documentation of hardware, software and datasetSWall40–52An outside reader rebuilds the receive chain from the documents
T6.5Review of patents and non-English literaturePI–40–44Review added to Chapter 2
T6.6Paper preparation and submissionPIall44–52Paper submitted (D6.2)
T6.7Public release of designs, code, dataset and reportSWall50–52Release published (D6.3); M5

9.4Milestones

Table 9.3.Milestones and acceptance criteria.

IDWeekMilestoneCriterionVerificationOwner
M118Calibration agrees with theorySpectra of the four calibration spheres agree with the exact model within ±10% in amplitude and ±5° in phase at all 12 tones, at 10 and 20 cmCalibration report D2.1, reproduced independently from raw data by DSPI
M226Positioning validatedTen passes over a marked target from different headings give positions within 2 cm (1σ); depth from peak width within ±1.5 cm at 20 cmValidation report D3.2SW
M336Classifier validated on unseen objectsBlind test: ferrous / non-ferrous accuracy at least 95%, shape class at least 85%, size within ±25% for at least 80% of objectsBlind-test report D4.3; objects hidden by HWDS
M440Radar imagingA metal can of about 10 cm buried at 35 cm in dry sand is detected and located; depth error at most 3 cm; echo polarity identified as metalRadar report D5.2HW
M552Fused demonstration and releaseLive fused survey of a seeded 5 m × 5 m plot; designs, software, dataset and report publishedPublic repository; field-trial report D6.1PI

9.5Decision gates

At each gate the team reviews the milestone evidence and chooses one of the prepared options. Decisions and their reasons are recorded in the decision log.

Table 9.4.Decision gates.

GateWeekConditionIf metIf not met
G118M1 metFull-tensor work (WP4) starts as plannedUp to 4 weeks of diagnosis of model or hardware; WP4 start moves accordingly, WP3 continues. If still not met in week 22, the dataset uses empirically calibrated spectra and the discrepancy is reported.
G226M2 metTracked dataset collection with the hand-held poleA wheeled cart with odometry replaces the hand-held pole; RTK used for start and end points of each track.
G336M3 metWP6 proceeds as plannedData collection extended by 4 weeks; the operator interface (T6.2) is reduced to a minimum.
G440M4 metRadar included in fusion and field trialsInduction-only results are published; the radar is reported as a partial result and future work.

9.6Critical path and dependencies

The critical path runs T1.2 → T1.5 → T2.2 → T2.4 → M1 → T4.1 → T4.4 → T4.5 → M3 → T6.1 → T6.3 → M5. Its slack is small: a delay in nulling the coils (T2.2) or in the calibration measurements (T2.4) moves the dataset collection and all later work. The positioning platform (WP3) and the radar (WP5) have about four weeks of slack each. The main external dependency is procurement of the RTK receivers and printed circuit boards, which is started in week 1 (T0.2).

Table 9.5.Procurement schedule.

ItemOrder in weekNeeded in weekRemark
Teensy 4.1, op-amps, passives, connectors12Local or fast-shipping distributors
Magnet wire, foil, coil formers12
Preamplifier PCB, first run46Design completed in T1.5
Class-D amplifier modules, sense resistors36
RTK receivers, antennas, radio link110Longest lead time, import
IMU, magnetometer, camera, ranger612
Calibration spheres, test objects, sandbox612
Vivaldi antenna PCBs, RF cables, coupler2024After simulation in T5.2
Second PCB run (revised preamp, tensor head)1620

9.7Deliverables

Table 9.6.Deliverables.

IDDeliverableTypeDue weekOwner
D0.1Project handbook: lab-log template, data conventions, safety rulesDocument3PI
D1.1Codec bring-up and characterisation reportReport5SW
D1.2Preamplifier and calibration-injector PCB, revision AHardware8HW
D2.2Static induction rig (1 TX + 3 RX), documentedHardware13HW
D2.1Calibration report: measured sphere spectra against the modelReport18PI
D3.1Positioning and timing platform with fusion softwareHardware, software24SW
D3.2Tracked-pass validation reportReport26PI
D4.2Tensor inversion softwareSoftware28PI
D5.1Radar hardware: antennas, amplifiers, couplerHardware33HW
D4.1Labelled dataset, version 1Data34DS
D4.3Classifier and blind-test reportReport36DS
D5.2Radar software and test reportSoftware, report40PI
D6.1Field-trial report of the fused systemReport48DS
D6.2Paper submitted to a journal or conferencePublication52PI
D6.3Public release: designs, code, dataset, reportRelease52SW

9.8Reporting and reviews